Complex Work, Carefully Managed
The groundwork and formwork contractor required additional specialist resources to accelerate the programme and maintain the completion deadline.
Kent Wharf was a major steel fixing project delivered for a valued existing client.
The original programme was scheduled over thirty-five weeks. Our team joined the works early and provided the additional resources needed to accelerate progress.
Following a request from the groundwork and formwork contractor, the team mobilised within twenty-four hours, maintained continuity on site and helped bring the development to completion five weeks ahead of programme.
High standards maintained at every stage.
Safe working practices throughout delivery.
Careful planning and accurate execution.
Focused on programme, budget and quality.
The groundwork and formwork contractor required additional specialist resources to accelerate the programme and maintain the completion deadline.
The team mobilised within twenty-four hours, took over the steel fixing package efficiently and maintained continuity of work on site.